Raised Fist0

Combined Work (A + B Together)

Start learning this pattern below

Jump into concepts and practice - no test required

or
Recommended
Test this pattern10 questions across easy, medium, and hard to know if this pattern is strong

Introduction

Combined work problems ask how long two or more workers (or machines) take when they work together. These problems are common because many real-world tasks are completed by teams - knowing how to add efficiencies correctly lets you estimate total time or shared contributions.

This pattern is important because it generalizes the basic formula W = R × T to multiple agents and forms the basis for more advanced mixture and collaborative work problems.

Pattern: Combined Work (A + B Together)

Pattern: Combined Work (A + B Together)

Key concept: Add individual one-day works (rates) to get the combined one-day work; then take reciprocal to find total time.

If A takes TA days and B takes TB days to finish 1 work individually:
One-day work of A = 1/TA, One-day work of B = 1/TB.
Combined one-day work = 1/TA + 1/TB.
Total time when both work together = 1 ÷ (1/TA + 1/TB).

Step-by-Step Example

Question

A can finish a job in 12 days. B can finish the same job in 8 days. If both work together, how many days will they take to complete the job?

Options:

  • A. 4.8 days
  • B. 4 days
  • C. 4.5 days
  • D. 5 days

Solution

  1. Step 1: Identify individual times and convert to one-day works.

    A’s one-day work = 1/12.
    B’s one-day work = 1/8.
  2. Step 2: Add the one-day works to get the combined rate.

    Combined one-day work = 1/12 + 1/8 = (2 + 3) / 24 = 5/24.
  3. Step 3: Invert the combined rate to find total time.

    Time = 1 ÷ (5/24) = 24/5 days = 4.8 days.
  4. Final Answer:

    4.8 days → Option A
  5. Quick Check:

    Check by multiplying time × combined rate: (24/5) × (5/24) = 1 (complete work) ✅

Quick Variations

1. More than two workers: add all individual one-day works (e.g., A + B + C = 1/TA + 1/TB + 1/TC).

2. One worker does part of the job first, then both work together - compute work done by the first part, subtract from 1, then use combined rate for remaining work.

3. Workers with different units (hours vs days): convert to the same time unit before adding rates.

4. When efficiencies given (e.g., A is k times as efficient as B), convert to rates using ratios and then compute combined time.

Trick to Always Use

  • Step 1 → Convert each person's time to one-day work (reciprocal).
  • Step 2 → Add all one-day works to get combined rate.
  • Step 3 → Invert the combined rate to get total time (Time = 1 ÷ combined rate).

Summary

For combined work problems:

  • Always convert times to one-day works first (use reciprocals).
  • Add rates (do not add times) to get the combined rate.
  • Take the reciprocal of the combined rate to find the time required when working together.
  • Use the same unit (days/hours) across all workers and include a quick check by multiplying time × combined rate to ensure the result equals 1.

Practice

(1/5)
1. A can finish a job in 6 days and B can finish it in 12 days. How long will they take to complete the work together?
easy
A. 4 days
B. 3 days
C. 5 days
D. 6 days

Solution

  1. Step 1: Identify the values.

    A's one-day work = 1/6; B's one-day work = 1/12.
  2. Step 2: Add rates.

    Combined one-day work = 1/6 + 1/12 = (2 + 1)/12 = 3/12 = 1/4.
  3. Step 3: Invert to get time.

    Total time = 1 ÷ (1/4) = 4 days.
  4. Final Answer:

    They finish the work together in 4 days → Option A.
  5. Quick Check:

    4 × (1/4) = 1 (complete work) ✅
Hint: Add individual one-day works and take reciprocal for total time.
Common Mistakes: Adding times directly instead of adding rates.
2. A can do a work in 10 days and B can do it in 20 days. Working together, how much work will they complete in one day?
easy
A. 1/10
B. 3/20
C. 1/15
D. 1/8

Solution

  1. Step 1: Identify the values.

    A's one-day work = 1/10; B's one-day work = 1/20.
  2. Step 2: Add rates.

    Combined one-day work = 1/10 + 1/20 = (2 + 1)/20 = 3/20.
  3. Final Answer:

    They complete 3/20 of the work in one day → Option B.
  4. Quick Check:

    Reciprocal time = 20/3 ≈ 6.67 days; (3/20) × (20/3) = 1 ✅
Hint: Add the reciprocals (1/T) to get combined one-day work.
Common Mistakes: Averaging times or using wrong LCM when adding fractions.
3. A and B can complete a work together in 8 days. If A alone can do it in 12 days, in how many days can B alone finish it?
easy
A. 18 days
B. 20 days
C. 24 days
D. 30 days

Solution

  1. Step 1: Identify the values.

    Combined one-day work = 1/8; A's one-day work = 1/12.
  2. Step 2: Subtract to find B's rate.

    B's one-day work = 1/8 - 1/12 = (3 - 2)/24 = 1/24.
  3. Step 3: Invert to get time for B.

    Time for B = 1 ÷ (1/24) = 24 days.
  4. Final Answer:

    B alone can finish the work in 24 days → Option C.
  5. Quick Check:

    1/12 + 1/24 = (2 + 1)/24 = 3/24 = 1/8 ✅
Hint: Find missing rate by subtracting known rate from combined rate, then invert.
Common Mistakes: Subtracting times instead of rates or mixing denominators incorrectly.
4. A and B together can finish a work in 9 days. A alone can finish it in 18 days. How long will B alone take to finish the same work?
medium
A. 15 days
B. 20 days
C. 12 days
D. 18 days

Solution

  1. Step 1: Identify the values.

    Combined one-day work = 1/9; A's one-day work = 1/18.
  2. Step 2: Subtract to find B's rate.

    B's one-day work = 1/9 - 1/18 = (2 - 1)/18 = 1/18.
  3. Step 3: Invert to get time for B.

    Time for B = 1 ÷ (1/18) = 18 days.
  4. Final Answer:

    B alone can finish the work in 18 days → Option D.
  5. Quick Check:

    1/18 + 1/18 = 2/18 = 1/9 ✅
Hint: Use 1/Tb = 1/Tcombined - 1/Ta, then take reciprocal.
Common Mistakes: Using subtraction on times rather than on their reciprocals (rates).
5. A and B can complete a piece of work in 5 days. If A alone can complete it in 15 days, how long will B alone take to complete it?
medium
A. 7.5 days
B. 6 days
C. 8 days
D. 10 days

Solution

  1. Step 1: Identify the values.

    Combined one-day work = 1/5; A's one-day work = 1/15.
  2. Step 2: Subtract to find B's rate.

    B's one-day work = 1/5 - 1/15 = (3 - 1)/15 = 2/15.
  3. Step 3: Invert to get time for B.

    Time for B = 1 ÷ (2/15) = 15/2 = 7.5 days.
  4. Final Answer:

    B alone can finish the work in 7.5 days → Option A.
  5. Quick Check:

    1/15 + 1/7.5 = (1 + 2)/15 = 3/15 = 1/5 ✅
Hint: Compute B's rate = combined rate - A's rate, then invert to get time.
Common Mistakes: Multiplying times directly or forgetting to use reciprocals when combining.