You want to improve your Kanban board to reduce task delays. Which combination of actions is best?

hard📝 Application Q8 of 15
Software Engineering - Agile and Scrum
You want to improve your Kanban board to reduce task delays. Which combination of actions is best?
ASet WIP limits and regularly review workflow bottlenecks
BRemove all WIP limits and add more columns
CAssign tasks randomly and avoid updating the board
DOnly track completed tasks and ignore in-progress tasks
Step-by-Step Solution
Solution:
  1. Step 1: Identify effective Kanban improvements

    Setting WIP limits controls flow; reviewing bottlenecks helps fix delays.
  2. Step 2: Evaluate other options

    Removing limits or ignoring tasks worsens delays; random assignment is ineffective.
  3. Final Answer:

    Set WIP limits and regularly review workflow bottlenecks -> Option A
  4. Quick Check:

    Limits + review = reduce delays [OK]
Quick Trick: Use WIP limits and review bottlenecks to improve flow [OK]
Common Mistakes:
  • Removing limits thinking it helps
  • Ignoring board updates
  • Random task assignment