A change request is submitted to add a new feature. After impact analysis, the team finds it will delay the project by two weeks. What should be the next step?

medium📝 Conceptual Q4 of 15
Software Engineering - Requirements Engineering
A change request is submitted to add a new feature. After impact analysis, the team finds it will delay the project by two weeks. What should be the next step?
AImplement the change immediately
BPresent the impact to stakeholders for approval
CReject the change without discussion
DIgnore the delay and continue as planned
Step-by-Step Solution
Solution:
  1. Step 1: Understand the role of impact analysis

    Impact analysis shows consequences like delays, which must be communicated.
  2. Step 2: Identify the correct next step after analysis

    The team should inform stakeholders and get approval before proceeding.
  3. Final Answer:

    Present the impact to stakeholders for approval -> Option B
  4. Quick Check:

    Next step after impact analysis = Stakeholder approval [OK]
Quick Trick: Always get stakeholder approval after impact analysis [OK]
Common Mistakes:
  • Implementing changes without approval
  • Rejecting changes without discussion
  • Ignoring project delays