Given the V-model, if the system design phase is completed, which testing phase should start next?

medium📝 Analysis Q4 of 15
Software Engineering - SDLC Models
Given the V-model, if the system design phase is completed, which testing phase should start next?
AIntegration testing
BUnit testing
CSystem testing
DAcceptance testing
Step-by-Step Solution
Solution:
  1. Step 1: Match system design with testing phase

    In the V-model, system design corresponds to integration testing on the testing side.
  2. Step 2: Identify testing order

    Unit testing corresponds to module design, so it comes before integration testing.
  3. Final Answer:

    Integration testing -> Option A
  4. Quick Check:

    System design pairs with integration testing [OK]
Quick Trick: System design phase pairs with integration testing [OK]
Common Mistakes:
  • Choosing unit testing instead of integration testing
  • Confusing system and acceptance testing

Want More Practice?