You have a project with unclear requirements that will evolve, and risk management is important. You want to combine iterative development with risk analysis. Which SDLC model should you choose?

hard📝 Application Q15 of 15
Software Engineering - SDLC Models
You have a project with unclear requirements that will evolve, and risk management is important. You want to combine iterative development with risk analysis. Which SDLC model should you choose?
AV-Model
BAgile
CWaterfall
DSpiral
Step-by-Step Solution
Solution:
  1. Step 1: Analyze project needs

    Unclear evolving requirements and risk management needs point to a model that supports iteration and risk analysis.
  2. Step 2: Match model features

    Spiral model combines iterative development with explicit risk assessment at each cycle.
  3. Final Answer:

    Spiral -> Option D
  4. Quick Check:

    Unclear requirements + risk = Spiral [OK]
Quick Trick: Evolving needs + risk? Spiral is best [OK]
Common Mistakes:
  • Choosing Waterfall despite unclear requirements
  • Confusing Agile with risk focus
  • Selecting V-Model which is rigid

Want More Practice?