Which of the following is the correct responsibility of the Scrum Master?

easy📝 Factual Q12 of 15
Software Engineering - Agile and Scrum
Which of the following is the correct responsibility of the Scrum Master?
AApproving the project budget
BWriting code for the product
CDeciding product features and priorities
DFacilitating Scrum events and removing impediments
Step-by-Step Solution
Solution:
  1. Step 1: Review Scrum Master role

    The Scrum Master helps the team follow Scrum practices and removes obstacles.
  2. Step 2: Match responsibilities

    Facilitating Scrum events and removing impediments is the Scrum Master's key duty.
  3. Final Answer:

    Facilitating Scrum events and removing impediments -> Option D
  4. Quick Check:

    Scrum Master = facilitator and blocker remover [OK]
Quick Trick: Scrum Master facilitates and clears blockers [OK]
Common Mistakes:
  • Confusing Scrum Master with Product Owner
  • Thinking Scrum Master writes code
  • Assuming Scrum Master controls budget