During a Sprint, the Development Team completes 20 story points. The Sprint Goal was to complete 25 story points. What is the best Scrum practice next step?

medium📝 Analysis Q4 of 15
Software Engineering - Agile and Scrum
During a Sprint, the Development Team completes 20 story points. The Sprint Goal was to complete 25 story points. What is the best Scrum practice next step?
ACancel the Sprint and start a new one
BExtend the Sprint duration to finish all work
CIgnore incomplete work and move on
DReview the incomplete work in Sprint Review and adapt
Step-by-Step Solution
Solution:
  1. Step 1: Understand Scrum handling of incomplete Sprint work and identify correct Scrum event for adaptation

    Scrum does not extend or cancel Sprints due to incomplete work; instead, the team reviews progress. The Sprint Review is where the team inspects completed and incomplete work and adapts the Product Backlog accordingly.
  2. Final Answer:

    Review the incomplete work in Sprint Review and adapt -> Option D
  3. Quick Check:

    Incomplete work handled in Sprint Review [OK]
Quick Trick: Use Sprint Review to inspect and adapt work [OK]
Common Mistakes:
  • Extending Sprint duration is against Scrum rules
  • Cancelling Sprint without urgent reason
  • Ignoring incomplete work harms transparency