Which of the following best describes the primary purpose of a Gantt chart in project management?
Think about what a timeline chart typically shows in a project.
A Gantt chart is mainly used to show the schedule of tasks over time, helping track progress and deadlines visually.
What does the 'critical path' in project scheduling indicate?
Consider which tasks directly affect the total time to complete the project.
The critical path is the longest chain of dependent tasks that sets the minimum project duration. Any delay here delays the whole project.
In a Gantt chart, if Task B cannot start until Task A finishes, what type of dependency is this?
Think about which task must finish before the other can begin.
Finish-to-Start means the second task starts only after the first task finishes, which matches the described dependency.
If a task on the critical path is delayed by 3 days, what is the impact on the overall project completion date?
Consider how delays on the critical path affect the total project time.
Delays on the critical path directly extend the project duration by the same amount of time.
You have a Gantt chart showing overlapping tasks. To shorten the project duration, which approach is most effective?
Focus on tasks that directly affect the total project length.
Shortening tasks on the critical path reduces the overall project duration. Other tasks do not affect the minimum completion time.