A team following Agile notices their sprint goals are often not met. What is a likely cause?

medium📝 Conceptual Q6 of 15
Software Engineering - Agile and Scrum
A team following Agile notices their sprint goals are often not met. What is a likely cause?
AProduct Owner is not attending meetings
BTeam members are working too fast
CDaily stand-ups are too short
DSprint backlog is too large or unclear
Step-by-Step Solution
Solution:
  1. Step 1: Analyze sprint goal failures

    When sprint goals are missed, a common cause is an overly large or unclear sprint backlog.
  2. Step 2: Evaluate options for likely cause

    Sprint backlog is too large or unclear correctly identifies this cause; other options are less directly related to missing goals.
  3. Final Answer:

    Sprint backlog is too large or unclear -> Option D
  4. Quick Check:

    Missed sprint goals = Large or unclear backlog [OK]
Quick Trick: Clear, manageable backlog helps meet sprint goals [OK]
Common Mistakes:
  • Blaming stand-up length
  • Assuming team works too fast