A project using the Waterfall model faces delays because the team tries to add changes after the design phase. What is the main issue?

medium📝 Analysis Q14 of 15
Software Engineering - SDLC Models
A project using the Waterfall model faces delays because the team tries to add changes after the design phase. What is the main issue?
AThe team should skip the testing phase
BThe project should have no design phase
CAdding changes is always allowed in Waterfall
DWaterfall model does not support easy changes after phases
Step-by-Step Solution
Solution:
  1. Step 1: Understand Waterfall model structure

    Waterfall is a linear model where each phase follows the previous one without going back easily.
  2. Step 2: Identify why delays happen

    Trying to add changes after design causes delays because Waterfall does not support easy backward changes.
  3. Final Answer:

    Waterfall model does not support easy changes after phases -> Option D
  4. Quick Check:

    Waterfall = no easy changes after phases [OK]
Quick Trick: Waterfall = linear, no backward changes [OK]
Common Mistakes:
  • Thinking changes are always allowed in Waterfall
  • Skipping testing phase to fix delays
  • Removing design phase to speed up