Which of the following is the correct order of events in a typical Agile sprint cycle?

easy📝 Factual Q3 of 15
Software Engineering - Agile and Scrum
Which of the following is the correct order of events in a typical Agile sprint cycle?
ASprint planning -> Sprint execution -> Sprint retrospective
BSprint retrospective -> Sprint planning -> Sprint execution
CSprint execution -> Sprint retrospective -> Sprint planning
DSprint execution -> Sprint planning -> Sprint retrospective
Step-by-Step Solution
Solution:
  1. Step 1: Recall the Agile sprint cycle order

    The sprint starts with planning, then execution, and ends with retrospective.
  2. Step 2: Match the correct sequence

    Sprint planning -> Sprint execution -> Sprint retrospective correctly lists planning first, then execution, then retrospective.
  3. Final Answer:

    Sprint planning -> Sprint execution -> Sprint retrospective -> Option A
  4. Quick Check:

    Sprint cycle order = Plan, execute, reflect [OK]
Quick Trick: Plan first, then do, then review [OK]
Common Mistakes:
  • Mixing up the order of retrospective and planning
  • Thinking retrospective happens before execution
  • Confusing sprint phases