During a Sprint, the team completes 8 user stories out of 10 planned. What is the Sprint velocity?

medium📝 Conceptual Q4 of 15
Software Engineering - SDLC Models
During a Sprint, the team completes 8 user stories out of 10 planned. What is the Sprint velocity?
A10 user stories
B8 user stories
C2 user stories
D18 user stories
Step-by-Step Solution
Solution:
  1. Step 1: Understand Sprint velocity definition

    Sprint velocity is the number of user stories or story points completed in a Sprint.
  2. Step 2: Calculate velocity from given data

    The team completed 8 user stories, so velocity = 8.
  3. Final Answer:

    8 user stories -> Option B
  4. Quick Check:

    Velocity = Completed work = 8 [OK]
Quick Trick: Velocity = work done, not planned [OK]
Common Mistakes:
  • Using planned stories instead of completed
  • Subtracting instead of counting completed
  • Adding planned and completed incorrectly