A team using the Spiral model forgot to perform risk analysis in the second cycle. What is the likely impact?

medium📝 Analysis Q14 of 15
Software Engineering - SDLC Models
A team using the Spiral model forgot to perform risk analysis in the second cycle. What is the likely impact?
AThe evaluation phase will be skipped as well
BThe project will automatically skip building in that cycle
CThe planning phase will be extended to cover risk analysis
DThe project will proceed without identifying new risks, increasing chances of failure
Step-by-Step Solution
Solution:
  1. Step 1: Understand role of risk analysis in Spiral model

    Risk analysis identifies potential problems early to reduce failure chances.
  2. Step 2: Analyze impact of skipping risk analysis

    Skipping risk analysis means risks may go unnoticed, increasing failure risk. Other phases are not automatically skipped or extended.
  3. Final Answer:

    The project will proceed without identifying new risks, increasing chances of failure -> Option D
  4. Quick Check:

    Skipping risk analysis = higher risk [OK]
Quick Trick: Skipping risk analysis raises failure risk [OK]
Common Mistakes:
  • Thinking other phases are skipped automatically
  • Assuming planning covers risk analysis fully
  • Believing evaluation is skipped too