Which of the following is the correct duration for a typical Sprint in Scrum?

easy📝 Factual Q3 of 15
Software Engineering - Agile and Scrum
Which of the following is the correct duration for a typical Sprint in Scrum?
A6 to 12 months
B1 to 4 weeks
C1 to 6 months
D1 to 2 days
Step-by-Step Solution
Solution:
  1. Step 1: Recall Scrum Sprint duration guidelines and eliminate incorrect durations

    Scrum recommends Sprints last between one and four weeks to maintain focus and adaptability. Durations shorter than a day or longer than a month reduce Scrum effectiveness.
  2. Final Answer:

    1 to 4 weeks -> Option B
  3. Quick Check:

    Sprint length = 1 to 4 weeks [OK]
Quick Trick: Sprints last 1-4 weeks for best results [OK]
Common Mistakes:
  • Choosing too short or too long durations
  • Confusing Sprint with release cycles
  • Assuming fixed 2-week Sprints only