Bird
0
0

If acceptance testing is successful in the V-model, which development phase was completed just before it?

medium📝 Analysis Q5 of 15
Software Engineering - SDLC Models
If acceptance testing is successful in the V-model, which development phase was completed just before it?
AModule design
BSystem design
CRequirements analysis
DCoding
Step-by-Step Solution
Solution:
  1. Step 1: Identify acceptance testing's corresponding phase

    Acceptance testing corresponds to the requirements analysis phase in the V-model.
  2. Step 2: Understand phase order

    Requirements analysis is the first development phase, so it precedes acceptance testing.
  3. Final Answer:

    Requirements analysis -> Option C
  4. Quick Check:

    Acceptance testing pairs with requirements analysis [OK]
Quick Trick: Acceptance testing matches requirements analysis phase [OK]
Common Mistakes:
  • Choosing coding or design phases instead of requirements
  • Mixing testing order

Want More Practice?

15+ quiz questions · All difficulty levels · Free

Free Signup - Practice All Questions
More Software Engineering Quizzes