Which of the following is the correct sequence in the iterative and incremental model?

easy📝 Factual Q12 of 15
Software Engineering - SDLC Models
Which of the following is the correct sequence in the iterative and incremental model?
ABuild -> Plan -> Test -> Design -> Repeat
BPlan -> Design -> Build -> Test -> Repeat
CTest -> Build -> Plan -> Design -> Repeat
DDesign -> Test -> Plan -> Build -> Repeat
Step-by-Step Solution
Solution:
  1. Step 1: Recall the iterative cycle steps

    The model follows a cycle of planning, designing, building, and testing in each iteration.
  2. Step 2: Confirm the correct order

    After testing, the cycle repeats to add more features or improvements.
  3. Final Answer:

    Plan -> Design -> Build -> Test -> Repeat -> Option B
  4. Quick Check:

    Plan, design, build, test, repeat = correct cycle [OK]
Quick Trick: Remember: plan before you build, then test [OK]
Common Mistakes:
  • Mixing up the order of steps
  • Thinking testing comes before building
  • Skipping planning phase