A team is using the iterative and incremental model but notices that the final product is missing some key features. What is a likely cause?

medium📝 Analysis Q6 of 15
Software Engineering - SDLC Models
A team is using the iterative and incremental model but notices that the final product is missing some key features. What is a likely cause?
AThey tested features too often during iterations
BThey completed all iterations too quickly
CThey used too many iterations
DThey did not plan iterations to cover all requirements
Step-by-Step Solution
Solution:
  1. Step 1: Analyze missing features cause

    Missing features usually mean incomplete planning or missed requirements in iterations.
  2. Step 2: Evaluate options

    They did not plan iterations to cover all requirements correctly identifies poor iteration planning as the cause.
  3. Final Answer:

    They did not plan iterations to cover all requirements -> Option D
  4. Quick Check:

    Missing features cause = Incomplete iteration planning [OK]
Quick Trick: Plan iterations to cover all requirements [OK]
Common Mistakes:
  • Blaming testing frequency
  • Assuming too many iterations cause missing features