How to Use Cron Syntax in Snowflake Tasks for Scheduling
To use cron in a
Snowflake Task, specify the schedule using the USING CRON clause with a standard cron expression. This expression defines when the task runs, such as every hour or daily at a specific time, and must be in UTC time zone.Syntax
The cron schedule for a Snowflake task uses the USING CRON clause followed by a cron expression string. The cron expression has five fields representing minute, hour, day of month, month, and day of week. The schedule runs in UTC time.
- minute: 0-59
- hour: 0-23
- day of month: 1-31
- month: 1-12
- day of week: 0-6 (Sunday=0)
Example: USING CRON '0 * * * *' UTC runs the task at the start of every hour.
sql
CREATE OR REPLACE TASK my_task WAREHOUSE = my_warehouse SCHEDULE = USING CRON '<cron_expression>' UTC AS <sql_statement>;
Example
This example creates a task that runs every day at 2:30 AM UTC and inserts the current timestamp into a table.
sql
CREATE OR REPLACE TABLE task_log (run_time TIMESTAMP); CREATE OR REPLACE TASK daily_task WAREHOUSE = my_warehouse SCHEDULE = USING CRON '30 2 * * *' UTC AS INSERT INTO task_log VALUES (CURRENT_TIMESTAMP()); -- To start the task ALTER TASK daily_task RESUME;
Output
Task daily_task created and scheduled to run daily at 2:30 AM UTC.
Common Pitfalls
Common mistakes when using cron in Snowflake tasks include:
- Not specifying
UTCtimezone, which causes confusion about run times. - Using six-field cron expressions (including seconds), which Snowflake does not support.
- Incorrect cron syntax causing task creation errors.
- Forgetting to
RESUMEthe task after creation, so it does not run.
sql
/* Wrong: Using seconds field (6 fields) and missing UTC */ CREATE OR REPLACE TASK wrong_task WAREHOUSE = my_warehouse SCHEDULE = '0 30 2 * * *' AS SELECT 1; /* Right: 5 fields and UTC specified */ CREATE OR REPLACE TASK correct_task WAREHOUSE = my_warehouse SCHEDULE = USING CRON '30 2 * * *' UTC AS SELECT 1;
Quick Reference
| Cron Field | Allowed Values | Description |
|---|---|---|
| Minute | 0-59 | Minute of the hour when task runs |
| Hour | 0-23 | Hour of the day (UTC) |
| Day of Month | 1-31 | Day of the month |
| Month | 1-12 | Month of the year |
| Day of Week | 0-6 | Day of the week (Sunday=0) |
Key Takeaways
Use the USING CRON clause with a 5-field cron expression and specify UTC timezone.
Cron expressions in Snowflake tasks do not support seconds; use minute to day-of-week fields only.
Always RESUME your task after creation to enable scheduling.
Check your cron syntax carefully to avoid errors during task creation.