Which of the following is the correct sequence of testing phases including system testing?

easy📝 Conceptual Q12 of 15
Testing Fundamentals - Testing Types and Levels
Which of the following is the correct sequence of testing phases including system testing?
AUnit testing -> Integration testing -> System testing -> Acceptance testing
BSystem testing -> Unit testing -> Integration testing -> Acceptance testing
CIntegration testing -> Unit testing -> System testing -> Acceptance testing
DAcceptance testing -> System testing -> Integration testing -> Unit testing
Step-by-Step Solution
Solution:
  1. Step 1: Recall testing order

    Testing starts with unit testing, then integration, then system, and finally acceptance testing.
  2. Step 2: Match sequence with options

    Only Unit testing -> Integration testing -> System testing -> Acceptance testing matches the correct order.
  3. Final Answer:

    Unit testing -> Integration testing -> System testing -> Acceptance testing -> Option A
  4. Quick Check:

    Testing order = Unit -> Integration -> System -> Acceptance [OK]
Quick Trick: Remember testing flows from small parts to whole system [OK]
Common Mistakes:
  • Mixing up the order of integration and system testing
  • Thinking system testing happens before unit testing
  • Confusing acceptance testing with system testing