During a sprint review, the team demonstrates completed features. Which of the following is NOT a typical outcome of this meeting?

medium📝 Analysis Q13 of 15
Software Engineering - Agile and Scrum
During a sprint review, the team demonstrates completed features. Which of the following is NOT a typical outcome of this meeting?
AAssigning daily tasks for the team members
BGathering feedback from stakeholders
CPlanning improvements for the next sprint
DCelebrating completed work and achievements
Step-by-Step Solution
Solution:
  1. Step 1: Understand sprint review goals

    Sprint reviews focus on showing work done, getting feedback, and planning improvements.
  2. Step 2: Identify which option does not fit

    Assigning daily tasks is done in daily standups or sprint planning, not sprint review.
  3. Final Answer:

    Assigning daily tasks for the team members -> Option A
  4. Quick Check:

    Sprint review ≠ assigning daily tasks [OK]
Quick Trick: Sprint review = feedback and demo, not daily task assignment [OK]
Common Mistakes:
  • Confusing sprint review with sprint planning
  • Thinking sprint review sets daily tasks
  • Ignoring the feedback and demo focus